Task Building Site: Week 32

The highlight of this week’s activities is the removal of the old plaster on the outside of the main building.  Patching the plaster where all the new windows have been installed will not look right.  The whole wall will be … Continue reading

Posted on February 20, 2012

Task Building Site: Week 31

The Team has been spending some time on the boundary walls, while the work inside is still progressing at a good rate.  The wall on the one side of the entrance to the property is almost done.  The brickwork looks … Continue reading

Posted on February 13, 2012

Task Building Site: Week 30

In Week 30 the motto is ‘Out with the old, in with the new’.  Starting with the main building seen from street side (corner of Davies St and Rhos St), there is a new door frame fitted downstairs, air ventilation … Continue reading

Posted on February 6, 2012

Task Building Site: Week 29

Work is going on all over the place now that permission has been given by The Owner to proceed with Phase II of the building project.  There are many activities in various parts of the buildings and also outside.  I … Continue reading